The Release Plan forecasts future velocity based on historical data. It’s created by the Product Owner who usually waits 2-3 sprints until some historical data has been generated. The input is the total effort in the product backlog, the team’s availability, sprint length and velocity. From this you can determine how many sprints are needed [...]